Lagoon Cell #3
Federal contribution
$43,923
Federal share25%
of $175.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
200620072008
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Yellow Grass
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Dec 19, 2007(actual)
Against the original forecast
- Construction start2 months earlyforecast Oct 15, 2005
- Construction end9 months lateforecast Mar 31, 2007