Water Treatment System
Federal contribution
$428,900
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Yellow Grass
- Construction start
- May 5, 2011(actual)
- Construction end
- May 31, 2012(actual)
Against the original forecast
- Construction start22 months lateforecast Jun 22, 2009
- Construction end10 months earlyforecast Mar 31, 2013
Also in Yellow Grass
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26909 in the federal list. How to read these figures.