Water Treatment Plant Expansion
Federal contribution
$114,720
Federal share25%
of $458.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
200620072008
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Biggar
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Feb 25, 2008(actual)
Against the original forecast
- Construction end11 months lateforecast Mar 31, 2007
Also in Biggar
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13051 in the federal list. How to read these figures.