Water Treatment Plant Expansion

Biggar, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$114,720
Federal share25%

of $458.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
200620072008
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Biggar
Construction start
Jul 31, 2005(actual)
Construction end
Feb 25, 2008(actual)

Against the original forecast

  • Construction end11 months lateforecast Mar 31, 2007

Also in Biggar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13051 in the federal list. How to read these figures.