Town of Biggar - Arena Ice Plant Solar Power Upgrade
Federal contribution
$59,973
Federal share40%
of $149.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Biggar
- Construction start
- Nov 15, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2021
- Construction end2 months lateforecast Apr 30, 2022
Also in Biggar
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59350 in the federal list. How to read these figures.