Montague Water Service Extension
Montague, Prince Edward Island
Federal contribution
$308,790
Federal share33%
of $943.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Montague
- Construction start
- May 15, 2006(actual)
- Construction end
- Sep 4, 2009(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 20, 2005
- Construction end2.8 years lateforecast Nov 15, 2006
Also in Montague
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13100 in the federal list. How to read these figures.