KCMH Interior and Exterior Repairs

Montague, Prince Edward Island

completeVentilationCVRIS
Federal contribution
$1.0M
$1,040,000
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 10, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Health PEI
Construction start
Sep 20, 2021(actual)
Construction end
Aug 30, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Jun 30, 2022