Eastern Realties Sanitary Sewer Phase II
Stratford, Prince Edward Island
Federal contribution
$284,660
Federal share33%
of $854.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Stratford
- Construction start
- Jul 16, 2006(actual)
- Construction end
- Oct 4, 2007(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 20, 2005
- Construction end12 months lateforecast Sep 29, 2006
Also in Stratford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13118 in the federal list. How to read these figures.