Water and Sewer Infrastructure Replacement - Corrugated Metal Pipe Replacement
Yellowknife, Northwest Territories
Federal contribution
$2.6M
$2,640,734
Federal share25%
of $10.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 10, 2005
2006200820102012
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Yellowknife
- Construction start
- Jul 19, 2005(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 30, 2005
- Construction end24 months lateforecast Mar 31, 2010