Water and Sewer Infrastructure Replacement - Corrugated Metal Pipe Replacement

Yellowknife, Northwest Territories

completeWastewaterMRIF
Federal contribution
$2.6M
$2,640,734
Federal share25%

of $10.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 10, 2005
2006200820102012
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Yellowknife
Construction start
Jul 19, 2005(actual)
Construction end
Mar 21, 2012(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 30, 2005
  • Construction end24 months lateforecast Mar 31, 2010