Norman Wells Water Storage Tank Replacement

Norman Wells, Northwest Territories

completeDrinking WaterMRIF
Federal contribution
$283,383
Federal share25%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 10, 2005
2006200820102012
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Norman Wells
Construction start
Jul 19, 2005(actual)
Construction end
Mar 21, 2012(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 1, 2005
  • Construction end4 years lateforecast Mar 31, 2008