Town of Altona/RM of Rhineland - Wastewater Treatment Facility Expansion
Federal contribution
$800,000
Federal share20%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 24, 2006
200620072008200920102011
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Altona
- Construction start
- Nov 17, 2005(actual)
- Construction end
- Jan 5, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 1, 2005
- Construction end3 years lateforecast Dec 31, 2007
Also in Rhineland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13168 in the federal list. How to read these figures.