Schedule
Announced and approvedApr 26, 2023
20232024
BuiltForecast
Approved 11 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Municipality of Rhineland
- Construction start
- Apr 1, 2024(actual)
- Construction end
- Sep 16, 2024(forecast)
Against the original forecast
- Construction start4 weeks lateforecast Mar 3, 2024