Vancouver Convention and Exhibition Centre Expansion

Vancouver, British Columbia

completeTourismCSIF
Federal contribution
$222.5M
$222,500,000
Federal share28%

of $808.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 4, 2002
ApprovedMar 22, 2004
2003200520072009
Built

Approved 16 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Nov 8, 2004(actual)
Construction end
Feb 15, 2009(actual)

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13177 in the federal list. How to read these figures.