Rapid Transit Fleet Expansion - SkyTrain Network
Federal contribution
$44.0M
$43,968,135
Federal share45%
of $98.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 23, 2018
201820192020
Built
Approved 5 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Metro Vancouver
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction end6 months earlyforecast Mar 31, 2021
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit stations and facilities$29.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51728 in the federal list. How to read these figures.