Toronto Transit Commission (TTC)

Toronto, Ontario

completePublic TransitCSIF
Federal contribution
$303.5M
$303,499,827
Federal share33%

of $910.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2004
20042007201020132016
Built
Program
Canada Strategic Infrastructure Fund
Construction start
Apr 1, 2004(actual)
Construction end
Jul 26, 2016(actual)

Against the original forecast

  • Construction start4 years earlyforecast Apr 1, 2008
  • Construction end2 months earlyforecast Sep 30, 2016

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13283 in the federal list. How to read these figures.