Mont-Tremblant
Federal contribution
$19.2M
$19,166,688
Federal share26%
of $75.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2004
20052007200920112013
Built
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Mont Tremblant Resort
- Construction start
- Dec 15, 2006(actual)
- Construction end
- Jun 30, 2013(actual)
Against the original forecast
- Construction end2.8 years earlyforecast Mar 31, 2016
Also in Mont-Tremblant
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13293 in the federal list. How to read these figures.