Purchase of 3 roof ventilation units
Federal contribution
$376,000
Federal share80%
of $470.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 9, 2024
2024
Built
Approved 19 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Mar 15, 2023(actual)
- Construction end
- May 30, 2023(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jan 15, 2023
- Construction end2 months lateforecast Mar 31, 2023
Also in Mont-Tremblant
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66729 in the federal list. How to read these figures.