completeBorder InfrastructureBIF
Federal contribution
$4.1M
$4,120,000
Federal share50%

of $8.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2004
200520062007
Built

Approved 5 weeks before the announcement.

Program
Border Infrastructure Fund
Ultimate recipient
Canadian Pacific Railway
Construction start
Dec 20, 2004(actual)
Construction end
Mar 31, 2007(actual)

Also in Windsor