Peter Pan Intersection Redesign and Construction

Charlottetown, Prince Edward Island

completeHighways and RoadsMRIF
Federal contribution
$1.1M
$1,086,780
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Aug 30, 2006(actual)
Construction end
Aug 1, 2007(actual)

Against the original forecast

  • Construction start11 months lateforecast Oct 13, 2005
  • Construction end7 weeks lateforecast Jun 15, 2007