Peter Pan Intersection Redesign and Construction
Charlottetown, Prince Edward Island
Federal contribution
$1.1M
$1,086,780
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 30, 2006(actual)
- Construction end
- Aug 1, 2007(actual)
Against the original forecast
- Construction start11 months lateforecast Oct 13, 2005
- Construction end7 weeks lateforecast Jun 15, 2007
Also in Charlottetown