Francis Lane Storm Piping and Sidewalk Construction

Charlottetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$112,057
Federal share33%

of $336.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Apr 10, 2006(actual)
Construction end
Aug 29, 2006(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 1, 2005
  • Construction end5 weeks earlyforecast Oct 1, 2006