Community of Alexandra, Community Centre Improvements

Charlottetown, Prince Edward Island

completeRecreationMRIF
Federal contribution
$21,366
Federal share33%

of $64.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 1, 2006(actual)
Construction end
Mar 30, 2008(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 20, 2005
  • Construction end8 months lateforecast Jul 31, 2007