Upgrades to Port Hope Water Pollution Control Plant

Port Hope, Ontario

completeWastewaterMRIF
Federal contribution
$4.9M
$4,930,413
Federal share33%

of $14.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008200920102011
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Port Hope
Construction start
Apr 20, 2006(actual)
Construction end
Oct 26, 2010(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 1, 2006
  • Construction end2.6 years lateforecast Mar 31, 2008

Also in Port Hope