Back to projects

Sanitary Sewer Twinning of the gravity sewer from Hope Street to the Sewage Treatment Plant to mitigate by-pass during wet weather events

Port Hope, Ontario

completeWastewaterCWWF
Federal contribution
$772,144
Federal share35%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Port Hope
Construction start
Sep 28, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2020

Also in Port Hope

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50194 in the federal list. How to read these figures.