Wellington Street Water and Sewer Main Reconstruction

St. Thomas, Ontario

completeWastewaterMRIF
Federal contribution
$302,800
Federal share33%

of $908.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
2007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of St. Thomas
Construction start
May 1, 2006(actual)
Construction end
Oct 1, 2010(actual)

Against the original forecast

  • Construction end3 years lateforecast Sep 30, 2007