Expansion of Leachate Control System - Green Lane Landfill

St. Thomas, Ontario

completeSolid Waste ManagementISF
Federal contribution
$1.5M
$1,452,508
Federal share32%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Oct 8, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2010
  • Construction end3 months lateforecast Aug 8, 2011