Evaluation and Expansion of Wastewater Storage Facilities
Federal contribution
$1.1M
$1,112,820
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2021
202120222023202420252026
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of St. Thomas
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Dec 31, 2025(forecast)