Construction of Mount Forest Wastewater Treatment Plant
Federal contribution
$4.5M
$4,464,884
Federal share33%
of $13.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Wellington North
- Construction start
- Apr 21, 2006(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 1, 2006
- Construction end5 months earlyforecast Mar 31, 2011
Also in Kenilworth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13667 in the federal list. How to read these figures.