Upgrades to Egremont Street Water System and Sanitary Sewer

Kenilworth, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$924,104
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Mar 15, 2010(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Mar 1, 2010
  • Construction end5 weeks earlyforecast Dec 15, 2010

Also in Kenilworth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27976 in the federal list. How to read these figures.