Crapaud Community Hall Renewal

Crapaud, Prince Edward Island

completeRecreationMRIF
Federal contribution
$114,416
Federal share33%

of $343.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Crapaud Community Hall Ltd.
Construction start
Apr 19, 2006(actual)
Construction end
May 16, 2008(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 20, 2005
  • Construction end10 months lateforecast Jul 31, 2007

Also in Crapaud