Crapaud Wastewater Treatmernt Facility Upgrades
Federal contribution
$520,901
Federal share32%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 3, 2008
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Community of Crapaud
- Construction start
- Dec 23, 2009(actual)
- Construction end
- Oct 18, 2013(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2010
- Construction end3.1 years lateforecast Aug 30, 2010
Also in Crapaud