Replacement of Kinch Street Bridge
Federal contribution
$172,518
Federal share33%
of $517.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Elizabethtown-Kitley
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Jul 17, 2009(actual)
Against the original forecast
- Construction start12 months lateforecast May 4, 2005
- Construction end2.3 years lateforecast Mar 31, 2007
Also in Elizabethtown-Kitley