Kitley Line 2 Reconstruction

Elizabethtown-Kitley, Ontario

completeHighways and RoadsISF
Federal contribution
$66,666
Federal share33%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 4, 2009(actual)
Construction end
Dec 15, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2011