Back to projects

Core Area Development Study, Phase 2

Stratford, Prince Edward Island

completeCapacity BuildingMRIF
Federal contribution
$66,667
Federal share33%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Stratford
Construction start
Oct 20, 2005(actual)
Construction end
Mar 31, 2008(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 1, 2005
  • Construction end18 months lateforecast Sep 30, 2006