Upgrading of Osceola's Waste Diversion Facility
Federal contribution
$59,662
Federal share33%
of $179.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Admaston/Bromley
- Construction start
- Jun 1, 2006(actual)
- Construction end
- Feb 11, 2009(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Mar 31, 2009
Also in Admaston/Bromley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13918 in the federal list. How to read these figures.