Reconstruction of Kennelly Road in Admaston/Bromley

Admaston/Bromley, Ontario

completeHighways and RoadsRNIS
Federal contribution
$673,578
Federal share60%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 22, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 21, 2020(actual)
Construction end
Oct 7, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 15, 2020
  • Construction end3 weeks earlyforecast Oct 31, 2022

Also in Admaston/Bromley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54102 in the federal list. How to read these figures.