Back to projects

Expansion of Landfill Site Capacity and Construction of on-Site Groundwater Treatment

McDougall, Ontario

completeSolid Waste ManagementMRIF
Federal contribution
$2.5M
$2,526,639
Federal share33%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of McDougall
Construction start
Apr 20, 2006(actual)
Construction end
Mar 12, 2009(actual)

Against the original forecast

  • Construction start7 months earlyforecast Nov 15, 2006
  • Construction end3 weeks earlyforecast Mar 31, 2009

Also in McDougall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13930 in the federal list. How to read these figures.