Replacement of Burnside Bridge
Federal contribution
$315,667
Federal share33%
of $947.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
2007200820092010
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of McDougall
- Construction start
- Apr 2, 2007(actual)
- Construction end
- Jun 29, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2010
Also in McDougall
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16656 in the federal list. How to read these figures.