Replacement of Bridge 4

Mono, Ontario

completeHighways and RoadsMRIF
Federal contribution
$251,682
Federal share33%

of $755.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008200920102011
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Mono
Construction start
Apr 20, 2006(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 1, 2005
  • Construction end3 months earlyforecast Mar 31, 2011