Back to projects

Replace existing water treatment control system at all three facilities to extend asset life through online asset management

Mono, Ontario

completeDrinking WaterCWWF
Federal contribution
$100,000
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2018201920202021
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2018(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast Jan 1, 2017
  • Construction end9 months lateforecast Mar 31, 2020

Also in Mono

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50179 in the federal list. How to read these figures.