Reconstruction of Mill Street Bridge
Federal contribution
$228,000
Federal share33%
of $684.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Orangeville
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Jun 10, 2009(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2005
- Construction end2.6 years lateforecast Oct 31, 2006
Also in Orangeville
- Dufferin County Administration and Provincial Offences Court Addition$2.7M
- Upgrading of the Water Pollution Control Plant$2.4M
- Rehabilitation of the West Sector Reservoir$2.0M
- Reconstruction of Roads and Services in the South Park and Village Green Subdivisions$1.6M
- New Transfer Terminal and Bus Acquisition$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13955 in the federal list. How to read these figures.