Extension of Ingersoll Street, Upgrade of Roads & Sanitary/Water Services to Support Toyota Complex
Federal contribution
$11.0M
$11,019,281
Federal share33%
of $33.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Oxford
- Construction start
- Apr 21, 2006(actual)
- Construction end
- Sep 29, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2006
- Construction end18 months earlyforecast Mar 31, 2011
Also in Oxford
- Structural relining of cast iron watermains at predetermined locations across the Ingersoll Distribution System$581.6K
- Rehabilitation of County Road 9$562.6K
- Expansion of the Dewatered Biosolids Winter Storage Building$469.3K
- Structural relining of 250 mm Cast Iron watermain on North Street - Broadway West to Woodland Crescent$376.0K
- Repair and rehabilitate 152 m of a deteriorating 750 mm trunk sewer that runs through the Brick Pond wetland$328.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13990 in the federal list. How to read these figures.