Repair and rehabilitate 152 m of a deteriorating 750 mm trunk sewer that runs through the Brick Pond wetland

Oxford, Ontario

completeWastewaterCWWF
Federal contribution
$328,218
Federal share48%

of $677.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201720182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Oxford
Construction start
Jan 3, 2017(actual)
Construction end
Jun 14, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Nov 1, 2016
  • Construction end4 weeks lateforecast May 17, 2019