Montreal Atwater and Charles-J.-Des Baillets Water
Federal contribution
$58.5M
$58,500,000
Federal share25%
of $234.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 2, 2005
ApprovedAug 31, 2006
200520072009201120132015
Built
Approved 16 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- City of Montréal
- Construction start
- Jun 21, 2008(actual)
- Construction end
- Dec 31, 2014(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 31, 2015
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14026 in the federal list. How to read these figures.