Automated meter Reading System
Norman Wells, Northwest Territories
Federal contribution
$61,324
Federal share26%
of $237.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20072009201120132015
Built
Approved 9.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Norman Wells
- Construction start
- Aug 23, 2006(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2006
- Construction end5 years lateforecast Mar 31, 2007