Convention and exhibition center of Lévis
Federal contribution
$4.1M
$4,053,768
Federal share33%
of $12.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2006
2007
Built
Approved 2 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Lévis
- Construction start
- Sep 15, 2006(actual)
- Construction end
- Jul 1, 2007(actual)