Northern Village of Pinehouse Arena

Pinehouse, Saskatchewan

completeSportMRIF
Federal contribution
$121,802
Federal share27%

of $445.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 1, 2006
2007200820092010
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 16, 2006(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction start14 months lateforecast Jun 1, 2005
  • Construction end3 months earlyforecast Mar 31, 2010

Also in Pinehouse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14320 in the federal list. How to read these figures.