Sewage Pump Station #3 & 4 Upgrades
Federal contribution
$300,000
Federal share50%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201720182019
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Northern Village of Pinehouse
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Dec 18, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end3 months earlyforecast Mar 31, 2019
Also in Pinehouse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48894 in the federal list. How to read these figures.