Inverness/Port Hawkesbury Wastewater Collection Distribution/Water Distribution
Federal contribution
$1.6M
$1,591,666
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of the County of Inverness
- Construction start
- Apr 28, 2006(actual)
- Construction end
- Dec 31, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 25, 2005
- Construction end3 months earlyforecast Mar 31, 2009
Also in Inverness
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14472 in the federal list. How to read these figures.