Municipality of the County of Inverness - Whycocogmagh Wastewater Treatment Plant Replacement

Inverness, Nova Scotia

approvedWastewaterGIS
Federal contribution
$2.4M
$2,350,618
Federal share9%

of $25.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 8, 2021
today
20202022202420262028
BuiltForecast

Approved 23 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Mar 22, 2027(forecast)
Construction end
Oct 31, 2028(forecast)