Water filtration plant upgrades

L'Île-Perrot, Quebec

completeDrinking WaterMRIF
Federal contribution
$300,000
Federal share5%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2007
2007200820092010
Built

Approved 7 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of L'Île-Perrot
Construction start
Sep 1, 2007(actual)
Construction end
Jul 31, 2010(actual)

Against the original forecast

  • Construction end20 months earlyforecast Mar 31, 2012

Also in L'Île-Perrot

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14501 in the federal list. How to read these figures.