Wastewater Treatment Plant Upgrade
Federal contribution
$5.4M
$5,380,000
Federal share13%
of $42.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
today
20212023202520272029
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- LÎle-Perrot
- Construction start
- Jun 30, 2026(forecast)
- Construction end
- Dec 31, 2028(forecast)
Also in L'Île-Perrot